Ireland’s Housing Crisis Deepens: Why Missing the 2030 Target by 100,000 Homes Could Trigger a Market Meltdown You Can’t Afford to Ignore
So here we are—eyeing the 2030 housing target like it’s the finish line of a marathon we might not quite cross. The government set out to build 300,000 new homes, but according to Deloitte’s latest Crane Survey, we’re gearing up to fall short by somewhere between 123,400 and 136,100 homes. Sure, 40,000 homes slated for completion in 2026 sounds like progress—up 10% from last year—but peel back the layers, and the story gets stickier. Approvals for planning permissions just aren’t keeping pace, and with a worrying chunk of them lapsing before breaking ground, the momentum feels more fragile than ever. It’s like trying to fill a leaky bucket—no matter how much water you pour in, it just don’t add up. The clock’s ticking, though, and Deloitte flags the next 12 to 18 months as make-or-break for turning permissions into actual construction. We’ve got potential in rezoned lands and a surge in student accommodations under construction, but the gap remains ominous. What’s your take? Can strategy and execution align fast enough to slam the brakes on this shortfall? Dive in to unpack the numbers and the nuances. LEARN MORE.
The government is projected to miss its 2030 target of building 300,000 new homes by between 123,400 and 136,100 homes, the latest Deloitte Crane Survey Report has found.
The study estimates that 40,000 homes will be completed in 2026, an increase of 10% year-on-year, meaning that 260,000 more homes are required if the 300,000 target is to be met.
However, maintaining the current level of momentum is not a given, according to Deloitte’s analysis, as the rate of planning permission approvals is not keeping pace.
Almost 182,130 homes have been granted planning permission in Ireland over the past five years, but Central Bank data for 2017-20 shows 25-32% of such permissions lapse without commencing construction.
Applying that ratio to the existing planning permissions figure would result in a predicted shortfall of 123,400-136,100 homes.
Even if all of the 40,000 homes expected to be completed in 2026 relate to planning permissions achieved outside the last five years, it would still leave a shortfall of 77,870.
Deloitte said the next 12-18 months will be critical to closing the gap between planning permissions being granted and construction starting.
“Even though our Crane Survey estimates that completions are on course to reach their highest volume since 2008, the planning permission pipeline is less promising,” said Kate English, chief economist at Deloitte Ireland.
“The high number of completions can also be attributed to the 2024 development levy waiver, which is due to expire this year. To avail of it, construction must be completed by 31 December 2026, and that will have driven completion figures up until this point.
“Section 28 guidelines, which instructed local authorities to zone more land for residential, is a step towards closing this planning permission pipeline gap. However, going forward, it is important that the viability of rezoned land is realistic and achievable.
“The figures in our report are a similarly sobering read for student accommodation, with there simply not being enough built or in the pipeline to meet current or forecasted demand.
“There is still an opportunity to turn this around, but it rests on what happens in the next 12-18 months.”
The research also shows there has been a decline in the delivery of new purpose-built student accommodation (PBSA) developments over the last two years.
Just 365 PBSA bedspaces were completed in 2025 across two schemes with 115 at Buckley House in Maynooth and 250 at The Artisan in Dublin 1.
This marked a decline from almost 900 bed spaces in 2024 and was well below the 10-year annual average of 1,620.
Completions in 2026 are set to improve only marginally, with 380 bed spaces across two schemes, as Ireland’s third-level enrolments are anticipated to peak at 247,600 students in the academic year of 2033/34 – up from 222,170 in 2025/26.
A total of 2,400 PBSA bed spaces were under construction across 11 schemes at the close of Q3 2026. This is up significantly from Deloitte’s previous Crane Survey report in Q1 2025, when just 1,400 bed spaces were under construction.
Bed spaces under construction are spread across Dublin (1,460), Galway (500), Cork (240) and Limerick (200). The largest scheme under construction at present is at University College Dublin’s Belfield campus, which will deliver 490 PBSA bed spaces.
The majority (72%) of bed spaces under construction are private schemes, with the remaining bed spaces being provided by third-level institutions.
Looking ahead, there are 11,875 PBSA bed spaces in developments that have secured planning permission, but the report says it is difficult to estimate what proportion of these will commence construction and ultimately add to PBSA stock.
Transaction volumes for hotels fell in the first half of 2025 following record activity levels in the previous two years.
There were seven transactions worth €82.75m, considerably lower than the €340m transacted in H1 2025.
A total of 2,080 hotel rooms are expected to be added to the market this year and 3,540 hotel rooms were under construction nationwide at the close of Q3 2026.
Among the hotel rooms currently under construction, 1,250 rooms are expected to reach completion in Q4 2026, including 470 at the Marriott Courtyard Inn on Dublin’s Abbey Street.
Construction activity continues to be concentrated in Dublin, with the capital accounting for just under 2,800 rooms, which is 79% of those under construction.
Next year, over 2,020 rooms are expected to come to market, with a further 250 rooms expected to complete in 2028. This figure is likely to increase as more projects commence construction in the coming year.
Further along the development pipeline, 11,550 hotel rooms have been granted planning permission. Dublin accounts for 72% of all rooms granted planning, and plans have been submitted for just under 1,200 hotel rooms nationwide.
In terms of Dublin office activity, the pipeline has contracted significantly. Beyond 2026, there will be no newly constructed speculative office space delivered to the Dublin market.
An estimated 93,900 sq m of new office space is expected to have been delivered by the end of 2026, including Citi’s new headquarters, KPMG’s new headquarters on Harcourt Street, and Enterprise Ireland’s new office at 160 Townsend Street.
Heading into 2027, just over 40,000 sq m of new and extensively refurbished office space will be under construction, including Deloitte’s new offices, 4 & 5 Grand Canal Square and IPUT’s 44-45 St. Stephen’s Green, which is due to be completed in 2027.

Looking ahead, there are a number of schemes ready to commence construction. Demolition work is ongoing at Florian, Adelaide Road, Dublin 2, with construction on a new 20,000 sq m scheme due to commence shortly.
Beyond that, market participants will be watching closely for signs of activity at Camden Yard, Dublin 8 (11,100 sq m) and 29 Earlsfort Terrace.
(Pic: Getty Images)